Key Takeaways
- The bridge opened in 1963 with three lanes each way. Its emergency shoulders were removed in the 1980s to add a fourth.
- More than $1 billion in federal grants came through the bipartisan infrastructure law, announced by Ohio Governor Mike DeWine and Kentucky Governor Andy Beshear.
- The estimate has grown from $3.6 billion to well over $4 billion. Material prices are up at least 60% from four years ago.
- The project is expected to create about 6 million hours of work and employ more than 700 skilled trades workers, with as many as 1,000 at its peak.
- The new companion bridge is a double-decker built beside the existing span. Traffic heading into Ohio will ride on the upper deck.
How it got here
The functionally obsolete label dates to the Clinton administration, five presidents ago. In 2004 the George W. Bush administration put $1 million toward planning and studies for a replacement. In 2011 President Obama stood in front of the bridge to promote his jobs bill, noting it carried about 150,000 vehicles a day. The federal grants that finally funded the project came 11 years after that.
What happens next
Construction is underway, and ODOT and the Kentucky Transportation Cabinet have released an animation of the build. Work starts rising in Northern Kentucky next year. The lower deck of the new bridge opens to traffic first, then the upper deck, which carries northbound traffic into Cincinnati. The existing Brent Spence is then reworked to carry local, non-interstate traffic.